Wall Cladding Procurement
Sintered Stone Wall Cladding Panel Layout: Joints, Openings and Installation Approval
A sintered stone wall cladding panel layout must connect the elevation grid, slab format, vein direction, joint positions, openings, corners, substrate and installation sequence. Approve every panel number and fixing zone before cutting begins.

Build the Elevation Grid First
Set the finished wall limits, project datum, floor line, ceiling line and centerlines before dividing the surface into panels. Place the main visual axis at the entrance, furniture centerline, reception desk, television, fireplace or other design focal point.
Match the elevation to available slab dimensions from the standard slab size guide. Include finished panel dimensions, cutting allowance, vein direction and the quantity required for replacement pieces in the layout schedule.
| Layout Control | Required Drawing Information | Approval Output |
|---|---|---|
| Primary Datum | Finished floor, ceiling and reference axis | Dimensioned elevation |
| Panel Grid | Horizontal and vertical joint coordinates | Numbered panel map |
| Pattern | Face, rotation, vein direction and sequence | Approved slab-to-panel map |
| Openings | Doors, outlets, screens, grilles and access panels | Coordinated opening schedule |
| Edges | Inside corners, outside corners, reveals and returns | Plan and section details |
| Fixing Zones | Substrate, rails, adhesive areas and mechanical points | Installation layout |

Coordinate Every Opening
- Door and window frames
- Electrical outlets and switches
- Displays, speakers and control panels
- Ventilation grilles and service access
- Shelves, brackets and mounted furniture
- Fireplace, plumbing and equipment interfaces
Dimension each opening from the project datum and adjacent panel joints. Record the finished opening, corner geometry, edge finish, backing requirement and installation clearance. Assign small removable panels to equipment requiring future access.
Plan Joints, Corners and Perimeters
Field Joints
Align repeated joints across the elevation and identify joint width, finish color and installation sequence.
Inside Corners
Show the meeting panel, visible edge, joint position and order of installation in plan.
Outside Corners
Specify the corner construction, return depth, exposed edge and face alignment with a section detail.
Floor Junction
Record the finished floor build-up, bottom line, skirting interface and installation clearance.
Ceiling Junction
Coordinate ceiling level, shadow gap, trim, lighting channel and top-panel access.
Material Transition
Detail the joint with timber, metal, glass, paint, doors, cabinetry and adjacent stonework.
Confirm the Substrate and Fixing Layout
Issue the substrate type, flatness record, framing or rail locations, fixing zones and panel loads with the wall elevations. Mark concealed services and restricted drilling areas.
State the bonding material, preparation method and application area in the installation specification. Coordinate material selection with the sintered stone adhesive guide.
Separate factory panel fabrication from locally supplied substrate, rails, anchors, trims, adhesive, lifting equipment and installation labor in the quotation.

Map Vein Direction and Panel Sequence
Assign a slab face and rotation to every visible panel. Mark the top edge, installation direction and adjacent panel numbers on the slab map, shop drawing and back label.
For mirrored elevations, align the center joint and paired faces with the bookmatched sintered stone layout. For repeatable project supply, approve current slabs through the batch consistency process.

Control Fabrication and Piece Labels
- Approve the elevation and slab-to-panel map.
- Release one controlled drawing revision.
- Cut panels by face number and orientation.
- Finish specified edges and openings.
- Dry-lay connected visual panels.
- Apply durable back labels and crate maps.
- Pack in installation or unloading sequence.
Site Survey Record
Measure the installation area after framing, substrate, floor, ceiling, door frames and adjacent finishes reach their coordinated positions. Reference every measurement to the project datum and released architectural drawings.
Overall Geometry
Finished wall width and height, diagonals, floor variation, ceiling variation and changes of plane
Substrate
Surface condition, flatness survey, panel joints, framing lines, rails and permitted fixing areas
Openings
Frame positions, equipment cutouts, outlet centers, access panels, grilles and service penetrations
Interfaces
Inside corners, outside corners, reveals, skirting, ceilings, cabinetry, metalwork and glazing
Site Access
Unloading point, lift, doorway, corridor, turning space, scaffold, lifting zone and work platform
Survey Control
Project, room, elevation, date, surveyor, drawing number, revision and approval signature
Installation Sequence and Hold Points
Release Substrate
Record framing, flatness, fixing zones, services and accepted corrective work.
Verify Delivered Panels
Match quantities, panel numbers, dimensions, orientation and crate position to the packing list.
Set Reference Lines
Transfer the project datum, first vertical joint, first horizontal joint and focal centerline to the wall.
Install by Sequence
Place panels in the numbered order and maintain the approved orientation, joints and perimeter conditions.
Close Interfaces
Complete corners, reveals, trims, access panels, outlets and transitions with adjacent trades.
Complete Inspection
Record alignment, joint consistency, pattern sequence, edge condition, cleanliness and completed protection.
Pre-Shipment Approval Record
Dimensions
Panel width, height, diagonals, openings, cutouts and edge locations
Appearance
Face, finish, tone, vein direction, rotation and adjacent-panel relationship
Fabrication
Edges, corners, returns, holes, slots, reinforcement and surface protection
Identification
Project, elevation, level, panel number, top direction and crate position
Complete the dimensional and visual review under the sintered stone quality inspection checklist. Connect the crate map and unloading sequence to the transportation requirements.
RFQ Information for Wall Cladding
Send the sintered stone wall cladding panel layout, plans, sections, panel schedule, selected design, slab format, thickness, finish, quantity, pattern direction, openings, edge details, substrate, fixing method, installation scope and destination.
State whether the order requires full slabs, cut-to-size panels or fully fabricated and labeled components. Add packing, spare-panel and delivery-sequence requirements to the item schedule.
Review sintered stone wall tiles, wall decoration slabs and large-format sintered stone slabs for the elevation schedule.

Request Wall Panel Layout Review
Send your elevations, panel schedule, slab selection, openings, substrate, quantity and destination for fabrication review and quotation.
Send Project DrawingsFrequently Asked Questions
What should a wall panel layout include?
Include the elevation datum, panel numbers, finished dimensions, joints, pattern direction, openings, corners, perimeter details, substrate, fixing zones and installation sequence.
How are wall panels identified?
Use one panel number across the elevation, slab map, fabrication drawing, back label, inspection record, crate map and installation plan.
How should bookmatched wall panels be approved?
Approve the A/B faces, centerline, panel order, rotation, joint positions and dry-layout image before fabrication release.
What controls a wall opening?
The coordinated drawing records the finished opening, location from the project datum, corner geometry, edge finish, clearance and backing requirement.
What should be checked before shipment?
Check panel dimensions, pattern sequence, finish, edges, openings, labels, surface protection, crate position and the packing list against the approved revision.